PMP認證考試練習題(二十一)(中英文)
1. Which of the following techniques can be used to integrate and measure a project’s schedule and cost performance? 要整合和衡量項目進度和成本績效,能用下列哪項技術方法: 2. A fully integrated project plan assists the project manager by: 完全整合的項目計劃對項目經理的幫助是通過: 3. The true status of a project cannot be determined unless which of the following are jointly considered: 要知道項目真實狀態,必須結合考慮下列哪一項: 4. Which of the following is not used for reporting performance? 下列哪一種技術沒有被用來報告績效: 5. Communication technology factors that may affect the project include all but which one of the following? 可能影響項目的溝通技術因素包括所有下列事項,除了: 6. The project manager issued a series of status reports over the course of several months to address issues that had emerged in project negotiations with the contractor. This represents what form of communication? 項目經理發出了關于數月來項目狀態一系列報告,用以表明在與合同方的項目談判中出現的問題,這表示的是什么形式的溝通: 7. Project management software: 項目管理軟件: 8. Debra realizes she must determine the aspects of her project that may be at risk. Which of following is not a useful tool for her to use in identifying these risks? Debra 認識到她必須決定項目可能在哪些方面有風險. 在識別這些風險中,下列哪一工具對她沒有什么用處? 9. Using the table below, the expected profit (or loss) of using the aggressive schedule is: 用下表數據計算,用積極的進度的預期的利潤 ( 或損失) 是: 10. An organization is considering bidding on a project in a new technology area with which it has no prior experience. The organization was able to locate knowledgeable experts in that field to help understand the new aspects. Therefore, probabilities can be assigned to possible profit or loss outcomes of this project. This would be an example of decision making under: 一個組織在考慮競標一個新技術領域的項目,但對該技術領域沒有經驗,組織能識別找出該領域知識專家來幫助理解這個新的領域. 因此,能夠確定該項目可能的利潤或損失結果概率. 這會是一個在什么條件下的決策例子: |