PMP考試每天一練-2020年PMP考試練習題143
PMP考試練習題一: A project manager wants to distribute the project charter to project stakeholders. Which method of communication should be used? A. Interactive B. Pull C. Push D. Face-to-face 項目經理希望將項目章程發送給項目干系人。應該使用哪一種溝通方法? A.交互式溝通 B.拉式溝通 C.推式溝通 D.面對面溝通 PMP考試答案解析:將文件發出去,這是推式溝通。 PMP考試參考答案:C PMP考試練習題二 A project management office (PMO) is presented with three project choices for implementation. Project A has an internal rate of return (IRR) of 12%, project B has a schedule performance index (SPI) of 0.8, and project C has a benefit-cost ratio (BCR) of 1.2. Based on this information, which of the following projects should be pursued? A. Project B B. Project C and B C. Project A D. Project C 項目管理辦公室(PMO)有三個項目可供選擇實施。項目A的內部收益率(IRR)為12%,項目B的進度績效指數(SPI)為0.8;項目C的效益-成本比(BCR)為1.2。根據這個信息,應選擇實施下列哪一個項目? A.項目B B.項目C和B C.項目A D.項目C PMP考試答案解析:項目C的BCR>1,項目可行。 PMP考試參考答案:D |