PMP考試每天一練-2020年PMP考試練習題145
PMP考試練習題一: During project execution, a project falls behind schedule. After evaluating options, the project manager concludes that temporarily collocating the most active virtual team members could bring the project back on schedule.What is the project manager doing? A. Developing the project team B. Managing the project team C. Optimizing the project team D. Balancing the project team 在項目執行期間,一個項目落后于進度計劃。在評估方案之后,項目經理得出結論,暫時讓最活躍的虛擬團隊成員集中辦公能讓項目恢復進度計劃。項目經理執行的是下列哪一項? A.建設項目團隊 B.管理項目團隊 C.優化項目團隊 D.平衡項目團隊 PMP考試答案解析:集中辦公是建設項目團隊的工具。 PMP考試參考答案:A PMP考試練習題二 A team member versa unable to attend the last project review meeting. The project manager confirms with the team reamer by phone that the project icon track and on budget. What should the team member consult to determine what task to perform next? A. Activity management plan B. Task management plan C. Project schedule D. Project calendar 一名團隊成員不能夠參加上一次項目評審會。項目經理用電話與該名團隊成員確認項目符合進度和預算。團隊成員應查閱下列哪一項來確定下一步要執行什么任務? A.活動管理計劃 B.任務管理計劃 C.項目進度計劃 D.項目章程 PMP考試答案解析:從項目進度計劃中查看活動的開始、結束以及持續時間,活動間的邏輯關系等。 PMP考試參考答案:C |