PMP考試每天一練-2020年PMP考試練習題146
PMP考試練習題一: During a project planning, the project team collects cost estimates, the delivery of major components and specific engineering duration. To calculate a distribution of possible outcomes for the total project, what technique should the project team use? A. Schedule network analysis B. Monte Carlo simulation C. Critical path method D. Resource leveling 在項目規劃期間,項目團隊收集成本估算,交付主要部件以及具體工程設計時間。若要計算整個項目的可能結果分布,項目團隊應使用什么技術? A.進度網絡分析 B.蒙特卡洛模擬 C.關鍵路徑法 D.資源平衡 PMP考試答案解析:蒙特卡洛:先確定每個活動的可能持續時間概率分布,進而算出整個項目的可能工期概率分布。 PMP考試參考答案:B PMP考試練習題二 A project manager is notified that a software developer for a critical section of code will be out of the office for three weeks. This task is not part of the critical path.What should the project manager do next? A. Continue with the tasks as stated in the project schedule B. Apply the responses described in the risk register C. Secure a backup resource with this skill D. Check the contingency plan 項目經理得到通知,代碼的關鍵部分軟件開發人員將離開辦公室三周時間。這項活動不屬于關鍵路徑。項目經理下一步應該怎么做? A.按照項目進度計劃的規定繼續任務 B.應用風險登記冊中所述的應對策略 C.獲得擁有該技能的備用資源 D.檢查應急計劃 PMP考試答案解析:識別到了風險,下一步應該查看風險登記冊中的應對策略。 PMP考試參考答案:B |