1、The project charter is developed by:

  A senior management

  B the customer

  C the project manager

  D both A and C

  E None of the above.

  ans:D

  2、A program is characterized as:

  A a grouping or related tasks lasting one year or less.

  B a unique undertaking having a definite time period.

  C a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.

  D a project with a cost over $1 million.

  E None of the above.

  ans:C

  3、Creation of project objectives:

  A allows for data collection and analysis and progress reporting against which standards of performance can be measured.

  B is accomplished by selection of measurable variables against which performance can be judged.

  C is required before funding of the project by the project sponsor.

  D all of the above.

  E A and B only

  ans:E

  4、A project is defined as:

  A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.

  B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.

  C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.

  D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.

  E All of the above.

  ans:A

  5、The use of the project reports:

  A are not necessary on small projects

  B provides a means whereby various levels of authority can judge project performance

  C provides insight into project areas and the effectiveness of the control systems

  D All of the above

  E B and C

  ans:E

  6、Documented work authorization provide:

  A a means of effective internal coordination of the project's activities.

  B an audit trail of all work authorized from project initiation to completion.

  C a means for communication of work activity between the project manager and the performing activities.

  D All of the above

  E A and B only.

  ans:D

  7、The project life-cycle can be described as:

  A project concept, project planning, project execution, and project close-out.

  B project planning, work authorization, and project reporting.

  C project planning, project control, project definition, WBS development, and project termination.

  D project concept, project execution, and project reporting.

  E All of the above.

  ans:A

  8、A Work Breakdown Structure:

  A assures all work is identified

  B subdivides the project into manageable segments

  C provides the project sponsor with a time-phase task summary

  D both A and B

  E All of the above.

  ans:D

  9、Scope Management:

  A entails managing the project's work content.

  B is a subset of configuration management and as such is performed by CM specialists.

  C is concerned with naming all activities performed, the end products which results and the resources consumed.

  D is not a concern of the project manager.

  E None of the above.

  ans:C

  10、Feasibility studies occur in which life cycle phase (s)?

  A Conceptual

  B Conceptual or Development

  C Execution

  D Preliminary planning

  E any life cycle phase

  ans:A

  11、Good project objectives must be:

  A General rather than specific

  B Established without considering resource bounds

  C Realistic and attainable

  D Overly complex

  E Measurable, intangible and verifiable

  ans:C

  12、Researching, organizing and recording pertinent information is called:

  A Alternative analysis

  B Information gathering

  C Configuration management

  D Post project analysis

  E All of the above

  ans:B

  13、The Work Breakdown Structure (WBS) is the basis for communicating:

  A Project scope, cost control, schedule, quality

  B Project objectives, dependencies, plan, cost control

  C Project scope, schedule, staffing, cost control

  D Project scope, quality, schedule, dependencies

  E Project budget, schedule, risk factors, work assignments.

  ans:A

  14、The sequential steps that define the process for successfully completing a project is:

  A Implementation Plan

  B a life cycle

  C Development Plan

  D a critical path

  E Management Plan

  ans:B

  15、What is the purpose of the Project Plan?

  A To document the Preliminary estimates.

  B To document the Definitive estimates.

  C To document the Budgetary estimates.

  D To document Parametric estimates.

  E To document Order of Magnitude estimates.

  ans:C

  16、Scope management is:

  A a project control function.

  B employs change control.

  C a work authorization process.

  D considers Cost, Quality and Schedule.

  E All of the above.

  ans:E

  17、Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

  A 5%

  B 10%

  C 15%

  D 25%

  E 50%

  ans:D

  18、Which of the following factors has historically been the greatest contributor to project failure?

  A Planning performed by a planning group.

  B Poor financial estimates.

  C Lack of sufficient management reserve.

  D Lack of management support.

  E Not using an automated tracking tool.

  ans:D

  19、Which of the following planning considerations is often overlooked?

  A Planning for project termination.

  B Qualified project manager assignment.

  C Insuring top management support.

  D Clearly defined tasks.

  E All of the above.

  ans:A

  20、The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

  A Conceptual

  B Development.

  C Execution

  D Finish

  E All of the above.

  ans:E