以下城市均已開通:
關閉
當前位置:PMP團購網 > PMP考試資料 > 正文

PMP考試題及參考答案(35)

轉載者:PMP團購網      發布時間:2012/7/24        點擊: 5428

1 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:

  A Multiplying the actual hours worked on the project by the budgeted labor rate.

  B Multiplying the budgeted hours to complete the task by the budgeted labor rate.

  C Dividing the actual hours required to complete the task by the budgeted labor rate.

  D Cannot be determined.

  E None of the above

  ans:B

  2 The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:

  A Feasibility studies.

  B Bills of materials.

  C Pert charts.

  D Managerial reserves.

  E None of the above

  ans:A

  3 The planned cost for the total project at its inception is called the _____.

  A Cost of goods sold.

  B Depreciable value.

  C Budgeted cost.

  D All of the above.

  E B and C only.

  ans:C

  4 Which of the following is not a measure of the profitability of a project or program?

  A Return on original investment.

  B Net present value.

  C Depreciation.

  D Discounted cash flow.

  E None of the above

  ans:C

  5 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.

  A Unauditable.

  B Undistributed.

  C Preauthorized.

  D Contingency.

  E In-process.

  ans:B

  6 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?

  A $3,000

  B $27,000

  C $27,270

  D $1,335

  E $1,000

  ans:E

  7 Using the situation stated in the Special window, the labor rate cost variance is:

  A $66,927

  B $68,329

  C $386

  D $-0

  E $18.36

  ans:D

  8 In project-driven companies, costs are usually billed againest the project based upon:

  A The burdened labor rate of the actual employees who performed the work.

  B The burdened labor rate of the line organization average salary.

  C The burdened labor rate of the company average salary.

  D The burdened labor rate of the average salary of the project team members.

  E None of the above.

  ans:A

  9 The most common method for pricing out non-burdened labor hours for a three year project would be to:

  A Price out the hours at the actual salary of the people to be assigned.

  B Price out the work using a company-wide average labor rate.

  C Price out the work using a functional group average labor rate.

  D All of the above.

  E A and B only.

  ans:C

  10 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:

  A Higher salaried employees were assigned.

  B Overtime was required.

  C The overhead rate increased.

  D Employee salaries had increased.

  E Any of the above

  ans:E

  11 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

  A The project will be completed late.

  B The critical path has been lengthened.

  C the costs are being overrun.

  D Overtime will be required to maintain the original critical path.

  E None of the above.

  ans:E

  12 Using the situation stated in the Special window, the total price variance of direct material is:

  A $80,245

  B $-4,236

  C $-3,479

  D $1

  E $83,994.00

  ans:C

  13 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

  A Become worse, become worse

  B Become worse, improved

  C Improved, increased

  D Improved, become worse

  E None of the above are correct

  ans:E

  14 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.

  A Trend line.

  B Trend analysis.

  C S curve.

  D Percent completion report.

  E Earned value report.

  ans:C

  15 Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.

  A Over, 16.66

  B Under, 16.66

  C Over, 10.0

  D Under, 10.0

  E None of the above.

  ans:A

  16 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

  A 1.1

  B 0.9

  C 0.956

  D 1.15

  E 0.869

  ans:A

  17 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

  A 0.875

  B 1.14

  C 0.952

  D 0.833

  E 1.2

  ans:B

  18 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

  A Element P

  B Element Q

  C Element R

  D Element S

  E None of the above.

  ans:C

  19 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

  A Element P

  B Element Q

  C Element R

  D Element S

  E None of the above.

  ans:D

  20 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

  A Direct labor dollars

  B Direct labor hours.

  C Overhead rates.

  D Procurement costs.

  E None of the above.

  ans:B

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
91涩漫在线观看