PMP考試題及參考答案(35)
1 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by: A Multiplying the actual hours worked on the project by the budgeted labor rate. B Multiplying the budgeted hours to complete the task by the budgeted labor rate. C Dividing the actual hours required to complete the task by the budgeted labor rate. D Cannot be determined. E None of the above ans:B 2 The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called: A Feasibility studies. B Bills of materials. C Pert charts. D Managerial reserves. E None of the above ans:A 3 The planned cost for the total project at its inception is called the _____. A Cost of goods sold. B Depreciable value. C Budgeted cost. D All of the above. E B and C only. ans:C 4 Which of the following is not a measure of the profitability of a project or program? A Return on original investment. B Net present value. C Depreciation. D Discounted cash flow. E None of the above ans:C 5 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget. A Unauditable. B Undistributed. C Preauthorized. D Contingency. E In-process. ans:B 6 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets? A $3,000 B $27,000 C $27,270 D $1,335 E $1,000 ans:E 7 Using the situation stated in the Special window, the labor rate cost variance is: A $66,927 B $68,329 C $386 D $-0 E $18.36 ans:D 8 In project-driven companies, costs are usually billed againest the project based upon: A The burdened labor rate of the actual employees who performed the work. B The burdened labor rate of the line organization average salary. C The burdened labor rate of the company average salary. D The burdened labor rate of the average salary of the project team members. E None of the above. ans:A 9 The most common method for pricing out non-burdened labor hours for a three year project would be to: A Price out the hours at the actual salary of the people to be assigned. B Price out the work using a company-wide average labor rate. C Price out the work using a functional group average labor rate. D All of the above. E A and B only. ans:C 10 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be: A Higher salaried employees were assigned. B Overtime was required. C The overhead rate increased. D Employee salaries had increased. E Any of the above ans:E 11 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that: A The project will be completed late. B The critical path has been lengthened. C the costs are being overrun. D Overtime will be required to maintain the original critical path. E None of the above. ans:E 12 Using the situation stated in the Special window, the total price variance of direct material is: A $80,245 B $-4,236 C $-3,479 D $1 E $83,994.00 ans:C 13 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. A Become worse, become worse B Become worse, improved C Improved, increased D Improved, become worse E None of the above are correct ans:E 14 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____. A Trend line. B Trend analysis. C S curve. D Percent completion report. E Earned value report. ans:C 15 Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent. A Over, 16.66 B Under, 16.66 C Over, 10.0 D Under, 10.0 E None of the above. ans:A 16 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is: A 1.1 B 0.9 C 0.956 D 1.15 E 0.869 ans:A 17 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is: A 0.875 B 1.14 C 0.952 D 0.833 E 1.2 ans:B 18 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150? A Element P B Element Q C Element R D Element S E None of the above. ans:C 19 Using the situation stated in the Special window, which WBS element is behind schedule but under budget? A Element P B Element Q C Element R D Element S E None of the above. ans:D 20 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control? A Direct labor dollars B Direct labor hours. C Overhead rates. D Procurement costs. E None of the above. ans:B |