1 The capacity to get an individual or group to perform a given task is described as:

  A Authority

  B Power

  C Influence

  D Leadership

  E Motivation

  ans:E

  2 A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.

  A 1,9

  B 9,1

  C 1,1

  D 9,9

  E 5,5

  ans:A

  3 Project leadership requires that the project manager pay attention simultaneously to the:

  A Tasks to be performed and needs of the team

  B Quantity and quality of the work to be performed

  C Efficiency and effectiveness of the team

  D Time, cost and performance deliverables

  E All of the above

  ans:E

  4 Which of the following can the project manager use as a means of measuring project team effectiveness?

  A Absenteeism

  B Sponsor-approved salary increases

  C Efficiency of the team

  D Turnover of personnel

  E Grievances

  ans:C

  5 Most project management leadership theories focus on all of the following except:

  A Personal characteristics of the project manager

  B The situation at hand

  C Personal traits of the subordinates

  D Behavioral styles of the project manager

  E Usefulness of authority and power in leadership

  ans:C

  6 Which theory(s) prescribes a form of participative management?

  A theory X

  B theory Y

  C theory Z

  D A or B

  E B or C

  ans:B

  7 In which of the following organization(s) does the Functional Manager have the LEAST authority?

  A coordinator

  B weak matrix

  C strong matrix

  D functional

  E expediter

  ans:C

  8 Project team building is most difficult in which type of environment?

  A weak matrix organization

  B strong matrix organization

  C projectized organization

  D functional organization

  E expediter organization

  ans:A

  9 The core function of the PM is

  A client interfacing

  B project integration

  C quality assurance

  D personal administration

  E All of the above.

  ans:B

  10 Which of the following is based on an individual identification with a more powerful person.

  A expert power

  B reward power

  C referent power

  D A and B.

  E A and C

  ans:C

  11 Which of the following results are Win/Win conflict resolution?

  A compromising

  B forcing

  C problem solving

  D smoothly

  E withdraw

  ans:C

  12 Which of the following organizations has the best technical project control?

  A matrix

  B functional

  C projectized

  D B and C

  E A and B

  ans:D

  13 The functional organization is effective with a mature product or single product line.

  A TRUE

  B FALSE

  ans:A

  14 The strong matrix versus a weak matrix.

  A team members are more likely to be assigned to the project office in a strong matrix

  B strong matrix is more difficult to manage.

  C the balance of power has shifted away from the PM.

  D functional managers no longer has control over the technical processes.

  E All of the above.

  ans:A

  15 The compromise conflict resolution technique

  A is necessary when both participants must win.

  B results in both sides losing

  C is used when resolution is more important than relationships

  D B and C

  E All of the above.

  ans:B

  16 A life cycle project manager tends to have the following characteristics:

  A balanced training

  B stronger administrative skills than technical skills

  C stronger technical skills than administrative skills

  D stronger human resource skills

  E None of the above.

  ans:B

  17 Which influence reflects an informal organization?

  A formal authority

  B reward power

  C referent power

  D expert power

  E penalty

  ans:C

  18 The type of power most infrequently used by the PM is

  A formal authority

  B reward power

  C referent power

  D expert power

  E penalty

  ans:A

  19 A key to successful Management by Objectives (MBO) is

  A insuring that employees have clearly defined objectives

  B involving employees in decision meetings

  C permitting employees to set their own objectives

  D allowing employees to perform their own evaluations

  E A or C.

  ans:E

  20 Delegation may

  A defer the decision on type of approach to be used.

  B be interpreted as passive and uncaring

  C tend to emphasize the task over the people involved.

  D be frequently utilized by a project manager.

  E All of the above.

  ans:E